How do I add allowances or add-alternates to my bid?

A guide to structuring optional scope (add-alternates) and managing budget placeholders (allowances) in Beam.

Overview

Add-alternates and allowances are both commonly used in construction proposals and contracts, but they serve different purposes and impact the contract value differently.

Add-alternates are optional scope items that the owner may choose to accept or reject. Their cost is not included in the base contract total. They are typically evaluated and selected during the proposal or contract award phase. If accepted, they increase the contract value. If not accepted, they do not impact the contract total.

Allowances are budget placeholders for scope that is not fully defined at the time of contract execution. The allowance amount is included in the total contract value. The final cost is determined later (e.g., when materials or selections are finalized). Any overage or savings is reconciled through a change order.


Feature Add-Alternate Allowance

Included in base
contract total

No Yes
Purpose Optional scope Placeholder budget
When finalized Before or at contract
execution
During construction

How value
typically changes

Base contract value
increases if selected
Adjusted via change order

How do they work in Beam?

As far as organization and formatting, both Add-Alternates and Allowances can be placed within a given scope group or in a dedicated "Add-Alternates" or "Allowances" section(s) at the bottom of the estimate.

Screenshot 2026-03-03 at 3.38.31 PM

In terms of contract value, Add-Alternates are normally excluded from the contract total and therefore the price can either be written in the description or recoded in the unit cost along with adjusting the quantity to 0. 

Add Alternate line items should have a Total (far right column) that is $0. 

Above: cost in description. Below: cost in unit cost with a quantity of zero.

Since allowances Allowances are normally included within the contract total, these can be handled just like typical line items where the unit cost, quantity, and total sections all have information. 

Allowance line items should have a Total (far right column) that reflects the total cost of the scope or item. 

Screenshot 2026-03-03 at 3.28.12 PM